Hi All,
Does anybody know how I can define multiple definitions of WorkingDayStart / End?
Basically, I want the calendar to have different working day hours per day, (eg, a Person works 09:00 - 17:30 Mon, Tue, Wed, but they work 09:00 - 19:00 Thu, Fri, Sat).
One idea I had was to try and set the background color of the individual cells, but am struggling to get / set the cell properties.