komal ![]() Newbie ![]() Joined: 15 February 2011 Status: Offline Points: 2 |
![]() ![]() ![]() ![]() ![]() Posted: 18 February 2011 at 12:11am |
Hi ,
WorkWeekView is showing Mon-Fri as working days.
Can i change the working days to Mon-Sat?
How can i change the working days?
|
|
![]() |
|
Xander75 ![]() Senior Member ![]() ![]() Joined: 26 April 2007 Status: Offline Points: 353 |
![]() ![]() ![]() ![]() ![]() |
Hi Komal,
You can change the WorkWeekView using the following line of code:
|
|
Product: Xtreme SuitePro (ActiveX) v15.3.1
Platform: Windows 7 64-bit (SP1) Professional Edition Languages: C#.Net using Visual Studio 2012 & Visual Basic 6.0 (SP6) |
|
![]() |
|
shalomb ![]() Newbie ![]() Joined: 23 January 2012 Location: Israel Status: Offline Points: 1 |
![]() ![]() ![]() ![]() ![]() |
CalendarControl.Options.WorkWeekMask = xtpCalendarDayMo_Fr + xtpCalendarDaySaturday
CalendarControl.Options.WorkWeekMask = 63 '111111 binary firs Sabbat 1 - Work , 0 - No Work
|
|
![]() |