Clicking on different dates causes the Calendar to show 1 resource and when clicking on other days shows all 4 resources. I have added 4 resources (names) to the Schedules table. What could I possibly check? I've spend hours trying to figure out the cause - Any help will be appreciated. I'm using very similar code as of the sample, it connects to an access database, and I've deleted all events. Even without events same problem. |
|
![]() |
|
vbuser ![]() Newbie ![]() Joined: 22 January 2004 Status: Offline Points: 39 |
![]() ![]() ![]() ![]() ![]() |
I finally fixed it by changing the name of the calendar from CalendrarControl to CalendarControl1 - that did it, dont know why...
|
|
![]() |
Post Reply ![]() |
|
Tweet
|
Forum Jump | Forum Permissions ![]() You cannot post new topics in this forum You cannot reply to topics in this forum You cannot delete your posts in this forum You cannot edit your posts in this forum You cannot create polls in this forum You cannot vote in polls in this forum |