Posted By: haitao
Subject: Highlight a day in workweek view
Date Posted: 17 August 2005 at 3:23pm

Hi,

  I tried to use showday method, it highlight the day I want but calendar changed to day view.

  Thanks for help!




Replies:
Posted By: sserge
Date Posted: 18 August 2005 at 7:58am
Hi!

ShowDay() method actually shows a single specified day.

Try to use AddDay() and ShowDays() methods.

In addition you can use SetSelection() method for highlighting.

--
WBR,
Serge


Posted By: haitao
Date Posted: 18 August 2005 at 9:52am
Thank you for the response. I have Version 9.70. I cannot find method SetSelection(). Thanks!


Posted By: sserge
Date Posted: 19 August 2005 at 8:23am
void CXTPCalendarView::SetSelection(const COleDateTime& dtBegin, const COleDateTime& dtEnd, BOOL bAllDayEvent);


Posted By: haitao
Date Posted: 19 August 2005 at 11:57am
Sorry, I am in the wrong board, I am working with VB.


Posted By: sserge
Date Posted: 20 August 2005 at 2:08pm
Unfortunately, this method is not currently available for VB. We'll add it for the next version.

--
WBR,
Serge